Overview

Land Unit was appointed by Midia Civil Engineering to deliver football pitch improvement works at Greenleys in Milton Keynes. The project involved preparing and improving the ground conditions for a football pitch, with works carried out in line with Sport England standards.

The project required a six-week build programme, followed by a 12-month maintenance period to help establish the football pitch and ensure the finished surface continued to develop to the required standard.

Do you have a project you need assistance with?

Get in touch today with us today.

Enquire with us

Challenges

Poor Ground Conditions – The existing ground conditions presented a key challenge, with the sub-base unable to filter water effectively. This caused issues with the drainage trenches breaking down and meant the football pitch required a more robust solution before it could perform as intended.

Drainage and Sub-Base Issues – The condition of the sub-base meant the site needed further preparation to create a stable foundation for the football pitch. Without this, there was a risk that future use and maintenance would be affected by poor drainage and inconsistent ground performance.

Long-Term Pitch Performance – As the project included a 12-month maintenance period, the works needed to be delivered with both immediate installation quality and long-term football pitch establishment in mind.

Solution

Land Unit addressed the challenges through a practical ground improvement and drainage-led approach:

Sub-Base Preparation – The team reviewed the ground conditions and recommended renewing the sub-base so it could properly support the football pitch and any future requirements.

Drainage Installation – Drainage stones were installed to improve water movement through the pitch construction and reduce the risk of the trenches breaking down again.

Specialist Machinery and Groundworks – The team used a range of machinery suited to the conditions on site, allowing the works to be delivered efficiently and to the required standard.

Cultivation, Seeding and Pitch Establishment – Following the drainage and sub-base works, the football pitch was cultivated and seeded. Secondary drainage was also included, along with sports equipment such as goals, to support the completed pitch installation.

Results

The project was delivered within the six-week build programme, with the football pitch then entering a 12-month maintenance period. Once the drainage improvements, machinery works and fine washed sand had been incorporated, the topsoil and surface condition showed a clear improvement.

The completed works provided a stronger foundation for the football pitch, improving drainage and helping the playing surface develop into a higher-quality finished area.

Key Takeaways

Improving Difficult Ground Conditions – Land Unit was able to respond to poor sub-base and drainage conditions with a practical solution that improved the long-term performance of the football pitch.

Drainage-Led Football Pitch Improvement – Primary drainage, secondary drainage, cultivation and seeding were all used to help create a more stable and resilient playing surface.

Ongoing Maintenance Support – The inclusion of a 12-month maintenance period helped ensure the football pitch continued to establish properly after the main build works were completed.

Reflections

The Greenleys project demonstrates Land Unit’s ability to identify and resolve challenging ground conditions on football pitch projects. By renewing the sub-base, improving drainage and supporting the pitch through an ongoing maintenance period, the team helped create a stronger, better-performing football pitch for long-term use.